Fangchenggang Thermal Power Plant – Phase I - 2 x 600MW
reporter:GXWEP   reporting time:2007-12-11 9:25:08 

Fangchenggang Thermal Power Plant is located in Fangchenggang city, Guangxi. The planned installed capacity is 2400MW, divided to 2 phases. Phase I is designed 2 x 600MW hypercritical coal-fired condensing steam turboset, together with high efficiency static dust extraction and desulfurizing units.
 
GXWEP has planned to invest 30% in the phase I project. Phase I commenced on March 18, 2005 and will be completed and put into operation by fist quarter of 2008.

 