GPCC:Less Day More Work!---No.1 Thermal Power Project of Liuzhou Steel Company
reporter:GXWEP   reporting time:2008-7-30 16:01:23 

May 14, established project office;
May 20, mobilized;
May 28, issued commencement order;
June 4, excavated power house;
June 8, placed concrete of boiler foundation;
June 27, assembled 200t track crane;
June 28, fabricated the first steel structure of boiler;
     ……
         These were construction progress of No.1 Thermal Power Project of Liuzhou Steel Company which is constructed by Guangxi Power Construction Company (GPCC).
Short construction period, small area and strict requirements are characteristics of No.1 Thermal Power Project of Liuzhou Steel Company. Manufacture and fabrication shall be completed within 195 days. All the work shall be performed in the space of 800 m2. And the foundation is almost filled soil and silt. Above records showed GPCC conquered varies of difficulties. Their next target is creating new record: less day, more work!

 